MISO 00002 Published On: 04/02/2024
Question: As you know, the MISO DPP interconnection application window is now open and will close on April 18th. To make strategic decisions about whether to submit for this year’s DPP cycle, we seek DEI’s guidance regarding the timeline fort shortlist notifications. Does DEI plan to release these notifications before the application window closes? Could you please provide the expected date for the release of these notifications? This information would be extremely beneficial in assisting us to manage our financial commitments effectively and to align our strategy with DEI.
Answer: No. CRA and Duke are working to evaluate the proposals and conduct additional due diligence. Bidders will be notified once the evaluation team is comfortable with the project rankings.